Yaqoub El-Jurf

Certifier BDC04915 · Sydney Wide Certifiers Pty Ltd

Activity

6
applications
0
duplexes
0
dwellings $1M+
6
approved / determined
0
withdrawn / rejected
17%
modifications
$18k
median cost
$901k
total value
9
median days to decision

Applications lodged 12 June 2026 to 26 Aug 2026 in the councils we follow.

Registration

Registration
BDC04915 · register entry
Status
Current
Class
Building Surveyor - Unrestricted
Current period
6 Aug 2026 to 5 Aug 2027
Registered since
6 July 2022 (4 years)
Insurance
Liberty Specialty Markets, to 25 Feb 2027
Checked
5 Oct 2026
Registration history (8)
6 Aug 20265 Aug 2027Building Surveyor - UnrestrictedRegistered
6 Aug 20255 Aug 2026Building Surveyor - UnrestrictedRegistered
6 Aug 20245 Aug 2025Building Surveyor - UnrestrictedRegistered
12 July 202411 July 2025Building Surveyor - Restricted (all classes of building)Registered
10 July 2024Building Surveyor - Restricted (all classes of building)Expired
10 July 20239 July 2024Building Surveyor - Restricted (all classes of building)Registered
6 July 2023Building Surveyor - Restricted (all classes of building)Expired
6 July 20225 July 2023Building Surveyor - Restricted (all classes of building)Registered

Contact

Address
30 Grose Street, PARRAMATTA NSW 2150
Phone
0451 036 708

Registration conditions

  1. Prior to the issue of a construction certificate or complying development certificate for a class 2-9 building, that is not required to be referred to Fire & Rescue NSW, under Part 3 - Division 3 of the Environmental Planning and Assessment (Development Certification and Fire Safety) Regulation 2021, the certifier must apply to the Commissioner of Fire & Rescue NSW, for a ‘FRNSW written report application’. However, the certifier is not required to refer a construction certificate application or a complying development certificate application to the Commissioner of Fire & Rescue NSW if:
    • a.The certificate is in respect of a stand-alone single storey class 5, 6, 7 or 8 building having a total floor area of 500m2 or less, and no alternative solution is proposed to a building standard that relates to a performance requirement in the BCA relating to fire safety.
    • b.The certificate is in respect of a class 2 to 9 building that is being renovated, altered, improved or repaired, and no performance solution is proposed to a building standard that relates to a performance requirement in the BCA relating to fire safety.
    • c.The certificate is in respect of a stage of building work to a class 2 to class 9 building, and the following provisions of the BCA Volume 1 do not apply to that stage; · Section C concerning fire resistance; · Section E Part E1 concerning fire fighting equipment; · Section E Part E2 concerning smoke hazard management.
Show 4 more conditions
  1. When applying to the Commissioner of Fire & Rescue NSW for a ‘FRNSW written report application’ under condition 1 above, the certifier must inform the Commissioner that the application is being made to comply with condition 1 imposed on this certificate of registration under the provisions of the Mutual Recognition Act 1992 (MR Act) and include a copy of the certifiers certificate of registration with the schedule of conditions for the information of the Commissioner.
  2. The certifier must not issue a construction certificate or complying development certificate for building work to which condition 1 applies unless the certifier has taken into consideration the report issued by the Commissioner of Fire & Rescue NSW. However, the certifier may issue a construction certificate or complying development certificate for a building to which condition 1 applies without obtaining a report from the Commissioner of Fire & Rescue NSW in the following circumstances:
    • a.If the Commissioner of Fire & Rescue NSW notifies the certifier that a report will not be provided, or
    • b.If the Commissioner of Fire & Rescue NSW fails to notify the certifier within 10 days after the receipt date of the application for report whether or not a report will be provided, or
    • c.If the Commissioner of Fire & Rescue NSW has given notice within 10 days of the date of receipt of an application for a report that a report will be provided, and a report is not provided within 28 days of the date the application for a report was received by the Commissioner.
  3. If the certifier does not adopt a recommendation contained in a report provided by the Commissioner of Fire & Rescue NSW, the certifier must:
    • a.notify the Commissioner, Fire & Rescue NSW; and
    • b.provide:
    • i.a copy of the construction certificate or the occupation certificate; and
    • ii.the reasons for not adopting a recommendation contained in the report.
  4. Within seven days of issuing an occupation certificate, in relation to a building that the certifier has been required to obtain a report from the Commissioner of Fire & Rescue NSW under condition 1 and which has been provided in accordance with the timeframes set by condition 3, the certifier must provide a copy of the occupation certificate to the Commissioner of Fire & Rescue NSW.

Councils

Canterbury-Bankstown
2
Northern Beaches
2
City of Sydney
1
Wollongong
1

Top suburbs

Lakemba
1
Belmore
1
North Narrabeen
1
Fairlight
1
Sydney
1
Unanderra
1

Duplex and dwelling ($1M+) applications